Time and Motion Study for Small Manufacturers: A Step-by-Step Guide

To run a time and motion study in a small factory, pick one repeating job, break it into short elements, time at least 10 cycles, adjust for the operator’s pace, and add allowances to get a standard time. Then watch how the work is physically done (walking, searching, waiting) and remove what adds nothing. You need a phone, a clipboard and two or three days, not a consultant’s software.

Key takeaways

  • Study one job at a time, ideally your bottleneck operation, not the whole factory at once.
  • Standard time = observed time × performance rating × (1 + allowances). Get any one part wrong and the target becomes unfair.
  • Time a pilot of about 10 cycles first; if the readings vary a lot, take 20 to 30 or more before you trust the average.
  • Occasional elements, like fetching a crate of blanks every 50 pieces, often cost more output than a slow operator does.
  • Tell the operator what you are doing and why before you start. A study that feels like policing gives you fake numbers.

What a time and motion study tells a small manufacturer

A time and motion study answers two questions: how long should this job take, and how much of the current effort is wasted? The time study part sets a standard time, the time a trained operator needs at a normal pace, with allowances for rest and unavoidable delays. The motion study part looks at how the work is done, so you can remove extra steps, reaching and walking.

For an owner, a reliable standard time is useful in four places: quoting job work, planning capacity, setting fair piece-rate or incentive targets, and spotting where a shift loses output. Without it, all four run on guesswork or on whatever the supervisor says. (Our time and motion study page explains how we run one with clients; this guide shows how to run your first one yourself.)

If you want the broader picture of how the whole process flows before timing a single step, start with business process mapping. Timing one machine perfectly does not help if the real delay is material reaching it late.

Before you start: the five things to prepare

Preparation decides whether your numbers mean anything. Spend half a day on it.

  1. Choose the job. Pick a repeating operation with a clear start and end, preferably the one where work piles up. A drilling, turning, pressing, stitching or packing station all work well.
  2. Fix the method first. The operator should be using the current standard method with the right tool, fixture and material. If the method changes next week, your study is out of date.
  3. Choose the operator. Pick someone trained and experienced on the job, not the fastest or the newest person.
  4. Explain the study. Tell the operator and supervisor that you are measuring the job, not the person, and that the goal is to remove hassles. Share the results with them.
  5. Get your tools ready. A stopwatch app or a phone video (video is easier, because you can replay and check), a printed observation sheet, and a measuring tape for walking distances.

Step by step: running the time study

The method below is the classic stopwatch time study, as taught in most work measurement courses, trimmed for a small unit.

Step 1: Break the job into elements. An element is a distinct part of the cycle with a clear start and end point, for example “pick blank and load fixture” or “unload and deburr”. Keep machine-controlled elements (the drill running on its own) separate from manual ones. Note occasional elements that do not happen every cycle, such as changing a crate or a tool.

Step 2: Run a pilot of about 10 cycles. Record the time for each element in each cycle. Write down every interruption (machine stop, phone call, material shortage) in a separate column instead of mixing it into the cycle times.

Step 3: Check the spread and decide how many more cycles to take. If the readings for an element sit within a narrow band, 10 to 15 cycles may be enough. If they swing widely, take 20 to 30 or more. Engineering courses use a statistical formula for this; a bigger sample on variable jobs is the practical version.

Step 4: Rate the operator’s pace. While observing, judge the pace against a normal pace of 100. An operator working briskly might be rated 110; one working slowly, 90. Machine-controlled elements are not rated, because the operator cannot speed them up. Rating is a judgement, so have the same person rate the whole study.

Step 5: Calculate normal time. For each element: average observed time × rating ÷ 100. Add up the elements, including occasional ones spread per piece.

Step 6: Add allowances. Allowances cover personal needs, fatigue and small unavoidable delays. They are usually a percentage added to normal time. Many textbooks use around 5% for personal needs alone, with fatigue and delay on top depending on how heavy, hot or awkward the job is. Agree one figure for your factory and use it consistently.

Step 7: Calculate standard time and output. Standard time = normal time × (1 + allowance). Pieces per shift = shift seconds ÷ standard time.

A worked example: a drilling station

Here is the method applied to a drilling operation on a small turned part. The numbers are illustrative, to show the arithmetic.

Element Avg observed time (s) Rating Normal time (s)
Pick blank, load fixture 7.0 90 6.3
Drill (machine-controlled) 14.0 not rated 14.0
Unload and deburr 9.0 110 9.9
Gauge check, place in tray 6.0 100 6.0
Fetch crate of blanks (180 s every 50 pieces) 3.6 per piece 100 3.6
Total normal time 39.8

With a 15% allowance, standard time is 39.8 × 1.15 = 45.8 seconds. In an 8-hour shift (28,800 seconds), that is about 629 pieces.

Now the motion study part. The operator walks about 25 metres each way to fetch blanks. If a helper or a trolley keeps a full crate beside the machine, that 3.6 seconds per piece mostly disappears. Normal time drops to 36.2 seconds, standard time to 41.6 seconds, and the standard shift output rises to about 692 pieces. That is roughly 60 more pieces a shift from moving a crate, not from asking anyone to work faster.

The trade-off: the fetching still has to happen, so you are moving it to a helper who can serve several machines at once.

Then compare the standard with your production register. If the register shows 500 pieces a shift against a standard of 629, the missing pieces are not hiding in the cycle. Look for waiting for material, setup and tool changes, power cuts, rework and long tea breaks. That list is usually where the money is.

The motion study: what to look for on the floor

Motion study is mostly careful watching. Video one full cycle and one hour of normal work, then go through it with the operator. Check for:

  • Walking: distance to material, tools, the weighing scale or QC. Sketch the path on the layout; a tangled line means the layout is fighting the work.
  • Searching: for a gauge, a spanner, the next job card. Shadow boards and fixed tool positions fix most of this.
  • Reaching and bending: bins on the floor, trays too far away. Raise and bring them closer.
  • Waiting: for a forklift, for a supervisor’s approval, for the next batch from the previous machine.
  • Double handling: parts put down and picked up again before the next operation.

For each one, write the fix, who owns it and the date. Then re-time the job after the change. The before and after numbers are what convince your supervisors.

Common mistakes that make the numbers useless

Most failed studies go wrong in the same few ways:

Mistake What happens Fix
Timing the fastest operator Standard is too tight, everyone else “fails” Use a trained, normal operator and rate pace
Mixing interruptions into cycle times Averages balloon, waste becomes the standard Log interruptions separately
Too few cycles on a variable job One odd reading distorts the result Pilot first, then extend the sample
No allowances Targets nobody can sustain over a shift Agree a standard allowance percentage
Studying before fixing the method You set a standard for a bad process Fix obvious waste, then time it
Keeping results from the floor Workers distrust the next study Share findings and fixes with the team

If the study shows that the real losses are in planning, material flow or reporting rather than the job itself, that is a systems question. Our manufacturing work often starts here, and the production visibility case shows what changes when owners can see output as it happens instead of in end-of-day reports.

Frequently asked questions

How long does a time and motion study take for one job?

For one repeating job with short cycles, observation usually fits within a shift or two, plus half a day to prepare and a day to calculate and agree fixes. Long-cycle jobs, such as fabricating a large assembly, take longer because you need enough full cycles to get a fair average.

What allowance percentage should I use?

There is no single correct figure. Textbooks commonly use about 5% for personal needs, with fatigue and delay allowances added depending on how heavy, hot or awkward the work is. Pick one documented figure for similar jobs in your factory and apply it consistently.

Will workers resist a time and motion study?

They may, especially if they fear tighter targets or pay cuts. Explain the purpose first, measure the job rather than the person, use a trained operator at a rated normal pace, and share the improvements you make to their workstation. Resistance drops when people see their own hassles being fixed.